Contracting Investor: EPCOR
Construction Dates: Sep 2017 – Nov 2017
As the Construction Manager at Risk, Auza Contracting installed over 2.4 miles of 12” waterline to provide EPCOR water to Luke AFB’s water distribution system. This project was completed in 12 weeks. The work included installation of multiple fire hydrants, air relief valves, blowoffs, and extensive asphalt removal and replacement.